Yes, there I was in the middle of the night at Dorval ready to pick up mu hire car when the company told me that it no longer had any Dodge Grand Caravans. The last one had been sold in the middle of the week, and there was now no longer ay car to offer me. Consequently they offered me a refund but that was no use whatever to me. I wanted a car and I would never have one over the counter at the ame price that I could book one in advance on the internet.
I was all of a clammy sweat when the alarm went off.
Rob turned up at about 08:45 (I’d alrzady been out working for 20 minutes) and Terry turned up at 09:00. By 09:30 we were sitting there waiting for the cement mixer which, true to form, didn’t turn up until 11:15.
It wasn’t anything like easy to come down here in reverse in his lorry but he managed it and 20 minutes later he had gone, minus 5 cubic metres of concrete.
Terry and Rob had left by 13:00 by which time we had done all we could. We were about half a dozen shovelfuls of concrete short.
Nevertheless we had the first row of breeze blocks of the retaining wall in poqition, the first row of concrete pillars and all of the reinforcing pylons in position.
This was a work and a half though and I’m pleased that I had two good friends to help me do all of this.
Hottest day of the year too (the water in the dump load was boiling) and I had a solar shower – I needed it too, especially after spending a couple of hours in the garden planting my aubergines and weeding the onions.
Now I’m having an early night as I’m having an early start tomorrow.